How long an interior design project takes: real timelines by stage

Алексей Гусев, генеральный директор студии АРТэврика

Author

Aleksei Gusev

Published

Reading time

5 min

For a property of around 100 m², an interior design project with prompt approvals takes about 2.5 months: the technical brief takes roughly two weeks, the concept design with layout and visualisation takes 20 working days or more, and the technical documentation takes a further 20 working days or so. For larger properties and more detailed styles, the range widens: the initial concept with references takes 5 to 15 working days, visualisation 15 to 40, and technical documentation 10 to 63. Below is the timeline for each stage and the main factor that, in practice, shifts the schedule more than the size of the property.

How long an interior design project takes on average — the short answer

For a property of around 100 m² with prompt approvals, an interior design project takes about 2.5 months — from the first meeting and site measurements to the handover of technical documentation. This period covers the technical brief, the concept design with layout and visualisation, and the technical documentation for the building team; the furnishing schedule is compiled in parallel and finalised after the drawings are handed over. This is a benchmark drawn from the studio's practice, not a universal formula: below is the timeline for each stage and what it actually depends on.

Timeline by stage

The technical brief is the first substantive stage: measurements, an assessment of the building services, zoning, and a concept with references. For a property of around 100 m² it takes roughly two weeks and ends with a signed document set that fixes the brief for all the following stages.

In the entrance hall, a low-angle view: graphic marble tile, warm wood and a built-in niche, daylight leading through to the living room
Entrance hall — project "Interior design of an apartment, 198 m²"

The concept design is the stage with the most decisions: it settles the layout, the spatial geometry, and the final visualisation with lighting. A typical property takes 20 working days or more; this is the stage where the furniture arrangement and the look of the interior can still be adjusted easily, so rushing it works against the project.

Living room with a wicker armchair by the panoramic window, graphic-print curtains and a rug, daylight highlighting the terracotta tones and warm-toned floor
Living room — project "Interior design of an apartment, 198 m²"

Technical documentation translates the approved design into drawings, details and specifications for the building team — a further 20 working days or so. The furnishing schedule does not wait for the final stage: it starts back at the technical brief and is finalised roughly a week after the technical documentation is handed over.

A contemporary en-suite in the guest bedroom: a recessed shower with a showerhead, glossy panels and a glass partition, soft lighting and a neutral grey-beige backdrop
Guest bedroom en-suite — project "Interior design of an apartment, 198 m²"

Stage

Timeline (property ≈ 100 m²)

Technical brief

≈ 2 weeks

Concept design (layout + visualisation)

20 working days or more

Technical documentation

≈ 20 working days

Furnishing schedule

finalised a week after the documentation is handed over

Total to the handover of technical documentation

≈ 2.5 months

Here is what this timeline looks like in practice, on a space-planning project for a developer, a separate and shorter type of work than a full interior design project: it started on 25 April 2025 and was handed over on 30 May. Within that month there were checkpoints of its own: on 5 May the target-audience profile was agreed, on 6–7 May the DWG base plan was reviewed and the measured survey was carried out, and from 12 to 20 May the draft layouts were developed. On projects with a partial redesign, the schedule is distributed differently: for example, in one apartment the main work was scheduled for handover in early September, with the decor finished afterwards.

Why the range is wider than the average figure

The figures above are a benchmark for a property of around 100 m² and a typical level of design complexity. In practice, the range by stage is noticeably wider: the initial concept with references takes 5 to 15 working days, visualisation 15 to 40, and technical documentation 10 to 63. The spread is driven not only by square metres but also by style: elaborate styles with a lot of non-standard furniture, decor and bespoke details stretch out the concept design stage and the technical documentation far more than extra floor area on its own.

What actually shifts the timeline

The size of the property is not the main lever that moves the schedule. The stages of an interior design project run sequentially: the layout is not started until the technical brief is signed off, and the technical documentation is not started until the visualisation is approved. Because of this sequence, a delay in the client's response at any stage shifts not just that stage but the whole remaining schedule. Prompt approvals are not a box-ticking exercise; they are the only real way to keep a project at the lower end of the range rather than the upper end.

How the project timeline relates to the renovation timeline

The interior design project timeline is the time before construction starts, not a substitute for it: the technical documentation, which takes up most of the cycle, is precisely the document that later governs the sequence of the renovation without on-site improvisation. A project fully worked out in drawings over 2.5 months usually saves time on site: changes are made on paper in hours rather than on site over weeks. A detailed breakdown of all seven steps of the process, from the first meeting to handover for construction, is in the article ‘Stages of an interior design project: from measurement to construction’.

How to get a timeline estimate for your own property

Average figures give a general idea, but the exact timeline depends on the specific floor area, layout and chosen style. The fastest way to estimate the schedule for your own property is at a consultation with a designer: that is also where you can discuss which elements of the chosen style can realistically fit the lower end of the range and which will need time closer to the upper end.

For more on what a full interior design project includes and how it compares to a renovation without one, see the article ‘Interior design project: the complete breakdown’.

Questions

Frequently asked questions

How long does an interior design project take on average?

For a property of around 100 m² with prompt approvals, it takes about 2.5 months from the first site visit to the handover of technical documentation. This is an average benchmark, not a fixed guarantee: the studio sets the exact timeline in the contract after the first meeting and measurements.

How much time does each stage take on its own?

The technical brief takes roughly two weeks. The concept design, where the layout and visualisation are approved, takes 20 working days or more. Technical documentation takes a further 20 working days or so. The furnishing schedule is compiled in parallel with the whole cycle and is finalised about a week after the technical documentation is handed over.

Why do interior design project timelines sometimes differ significantly from the average?

The average figures are calculated for a property of around 100 m² and a typical level of design complexity. In practice, the range is wider: the initial concept with references takes 5–15 working days, visualisation 15–40, and technical documentation 10–63. The spread is determined by the size of the property and the number of bespoke solutions: elaborate styles with a lot of non-standard furniture and custom details need more time at every stage.

What most often shifts the timeline — the size of the property or something else?

The floor area sets the volume of work, but the schedule depends more on how quickly the client approves each decision. The stages run sequentially: the layout is not started until the technical brief is signed off, and the technical documentation does not start until the visualisation is approved. A delay in responding at any stage pushes the whole schedule back, not just that stage.

Can an interior design project be sped up if the timeline is critical?

The substantive stages — measurements, layout development, building services — cannot be compressed without losing the quality of the decisions: this is where the result is set, and it is difficult and costly to redo later. The real reserve of time lies in how quickly the client approves each stage: a prompt response at every step keeps the project at the lower end of the range rather than the upper end.

Practice

Journal

Related articles

Living room with a gold-leaf panel and armchairs in textured upholstery

Process

Interior design project: a full breakdown

What an interior design project is, what it consists of and how long it takes: the layout, 3D visualisation, technical documentation and procurement schedule, with timelines for a property of around 100 m², from ARTEVRIKA studio.